Thursday, November 14, 2024
HomeTravel NewsThe progress of The completion of Uganda's Second International Airport

The progress of The completion of Uganda’s Second International Airport

The construction of Uganda’s second international airport, Kabale International Airport located in Hoima, entered its first phase in 2018 and has now achieved 96.1% completion. The project, designed to drive significant economic growth, is anticipated to be completed by August 13, 2025. This ambitious infrastructure project promises to be a transformative asset for Uganda, impacting multiple sectors including petroleum, tourism, and agriculture.

Strategic Importance of the Airport

The new airport’s construction aligns with Uganda’s strategic plans to diversify and strengthen key economic sectors. By providing a modern and efficient transport hub, the facility is set to become a crucial gateway for Uganda’s nascent petroleum industry. Located in proximity to the Albertine Graben, Uganda’s petroleum-rich region, the airport will facilitate the transport of materials, personnel, and equipment essential for petroleum extraction, refining, and export activities. This accessibility is expected to increase investment and expedite development within Uganda’s oil and gas sector, a significant area of potential revenue for the country.

In addition to supporting the petroleum sector, the airport will play a pivotal role in boosting Uganda’s tourism industry. Known for its national parks, wildlife, and unique attractions, Uganda will benefit from increased visitor access and convenience, which could attract more tourists from around the world. Agriculture, another key pillar of Uganda’s economy, is also set to benefit. With better transportation infrastructure, farmers and exporters will have easier access to international markets, making it simpler to export agricultural products directly from the region.

Also Read:Kabalega International Airport Almost Complete

Project Financials and Operational Readiness

The remaining project activities will require an estimated UGX 76.1 billion to reach completion. These activities are part of the Operational Readiness, Activation, and Transition (ORAT) process, an essential phase for ensuring that the airport is fully prepared to begin operations on schedule. ORAT activities include the testing of all systems, training of staff, and the operational readiness of logistics and equipment, all of which will contribute to the seamless transition from construction to full functionality.

Projected Economic Impact

The new international airport is expected to enhance Uganda’s regional competitiveness and establish it as a transportation hub for East Africa. The airport’s completion will also create new employment opportunities, both directly in airport operations and indirectly in sectors benefiting from increased international access. Moreover, by bolstering connectivity, the airport can drive down logistics costs, improving supply chain efficiencies for businesses and ultimately benefiting consumers.

As Uganda approaches the final stages of constructing its second international airport, the nation stands on the cusp of a new era in infrastructure. The projected completion date of August 13, 2025, signals a transformative milestone for Uganda’s economy, providing a launchpad for future growth in petroleum, tourism, and agriculture. Once completed, the new airport will position Uganda as a key player in East Africa’s transportation and economic landscape, offering sustainable growth opportunities across multiple sectors.

RELATED ARTICLES
Advertisementspot_img

Latest Articles

Recent Comments